Bringing new energy to the heart of our city

The Lichfield City Centre Cinema Development is one of the District Council’s flagship regeneration projects. The former Debenhams building at Three Spires Shopping Centre is being transformed into a new Everyman cinema alongside food, drink and social spaces.

A catalyst for city centre regeneration

The development represents an important step in our long-term vision to create a thriving, modern city centre that complements Lichfield’s rich heritage.

By introducing new leisure and hospitality opportunities, the scheme will:

  • Increase footfall and support local businesses
  • Enhance the evening and visitor economy
  • Provide new social and cultural experiences
  • Encourage further investment in the city centre

Development updates

We are committed to keeping residents, businesses and stakeholders updated as the development moves forward.

Works continue to progress on the redevelopment of the former Debenhams building into Lichfield’s new Everyman Cinema and leisure destination. Current activity includes:

  • Installation of the roof covering and glazing to the new terrace.
  • Windows being fitted across the first floor.
  • Brickwork continuing around the ground-floor glazing.
  • Internal walls and dry lining due to begin as the next stage of the works.

Construction programmes may change as works progress. Further updates will be shared as key milestones are reached.

Project timeline:

MSCP demolition, clearance and site landscaping

Spring 2024 - Winter 2024

Completion 100%

Cinema site mobilisation and demolition works

Winter 2024 - Summer 2025

Completion 100%

Groundworks and drainage install

Summer 2025 - Autumn 2025

Completion 100%

Superstructure works - alterations to external walls

Autumn 2025 - Winter 2025

Completion 100%

Fire protection works and stairways install

Spring 2025 - Summer 2026

Completion 100%

Major steelwork, roofing, drainage and Façade works

Summer 2026 - Autumn 2026

Completion 80%

Frequently Asked Questions

Why is the project important?

How is the project being funded?

Why were additional funds required?

When will the cinema open?

What will the development include?

Why was the multi-storey car park demolished?

Where can I find future updates?

Site Working Hours

Monday to Friday 7:30am – 5:30pm